10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The ACRP-PM exam has 60 questions and runs 1 hours 30 minutes.
These 10 free ACRP-PM questions are organized by exam domain, so you can see how each part of the ACRP Project Manager (ACRP-PM) Specialty blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Ethical and Participant Safety Considerations 10% of exam
Question 1
An 11-year-old agrees to join the main trial but refuses an optional research-only blood draw after an age-appropriate explanation. The investigator confirms that the child understands the choice. The parent has given permission for both activities. The approved protocol allows participation without the optional sample, which offers no direct clinical benefit. How should the site's procedure plan reflect these decisions?
Show answer & explanation
Correct answer: D - Omit the optional draw, document the refusal, and continue the main-trial activities covered by parental permission and the child's assent.
Domain 2: Regulatory Affairs 10% of exam
Question 2
A sponsor receives a report of unexpected bronchospasm requiring urgent treatment to prevent respiratory failure during an investigational-drug trial. The participant was discharged without inpatient admission. The investigator documents a medically important event and a reasonable possibility of drug causation, but confirms that it was not life-threatening when it occurred. The sponsor has all minimum reporting information today. Under ICH E2A, which expedited-reporting category and maximum initial-report timeline apply?
Show answer & explanation
Correct answer: B - A serious, non-life-threatening unexpected reaction, with an initial report no later than 15 calendar days after today's receipt.
Domain 3: Clinical Trial Operations 25% of exam
Question 3
Trial-wide primary-endpoint missingness is 3%, below a trial's prespecified 5% quality tolerance limit. One site's rate is 18%, above the monitoring plan's 10% site-level investigation trigger. Both measures include only participants whose endpoint window has closed. No immediate safety threat is identified. How should the project manager respond to this combination of results?
Show answer & explanation
Correct answer: C - Initiate a targeted review of the site's endpoint collection and act on the findings.
Question 4
Wrong-version consent forms recur after a corrective and preventive action plan has retrained every coordinator and updated the central document portal. Review of the affected visits shows that staff printed obsolete blank templates from local clinic drives. Staff can accurately explain the consent requirements. Which revision most directly addresses the demonstrated cause of recurrence?
Show answer & explanation
Correct answer: B - Retire obsolete local templates and verify the approved version before each consent discussion.
Question 5
User acceptance testing for a nonurgent protocol amendment finds that unanswered electronic symptom questions are stored as zero. The trial's rating scale runs from 0, meaning no symptoms, to 10, meaning the worst imaginable symptoms; an unanswered question must remain missing. Required approvals and staff training are complete, but the new forms have not been deployed. The release decision should be:
Show answer & explanation
Correct answer: A - Correct and retest the handling of unanswered questions before authorizing deployment.
Domain 4: Study Management 30% of exam
Question 6
A recruitment campaign begins reaching a broader audience. Referrals increase, but the screen-failure proportion rises from 24% to 61%, and randomizations fall behind target. Among candidates confirmed eligible, 92% still proceed to randomization. Time from eligibility confirmation to randomization and early participant retention are unchanged. Where would an additional recruitment investment most directly address the emerging bottleneck?
Show answer & explanation
Correct answer: A - Revise referral prescreening around the eligibility criteria responsible for the additional screen failures.
Question 7
Two activities start together for a site's activation: contract execution takes 12 elapsed days and laboratory qualification takes 9. Site initiation and final release then take 3 days and cannot start until both activities finish. There are no other dependencies. The sponsor needs activation within 13 elapsed days. Each proposed acceleration is feasible, costs the same, and preserves all required checks. Which proposal achieves the requested date?
Show answer & explanation
Correct answer: C - Shorten contract execution by 2 days, leaving laboratory qualification and site initiation unchanged.
Domain 5: Scientific Concepts and Research Design 10% of exam
Question 8
During review of a trial's electronic data-capture design, the project manager notices that selecting 'study drug discontinued' automatically closes all later efficacy-assessment forms. The primary estimand uses a treatment-policy strategy for drug discontinuation. The protocol permits participants who stop drug to continue the scheduled assessments, and their consent covers that follow-up. Which design requirement follows from the estimand?
Show answer & explanation
Correct answer: A - Keep scheduled outcome forms available when treatment stops but consented follow-up continues.
Domain 6: Business Management, Leadership, and Professionalism 15% of exam
Question 9
At quarter-end, a trial has paid $240,000 for completed work. Another $60,000 of accepted services has not been invoiced. Open purchase orders total $200,000 and already include those $60,000 of accepted services; the balance covers future contracted work. Completing the study will also require $40,000 of work not yet contracted. No other costs are expected. Against an approved total budget of $450,000, what forecast should be presented to leadership?
Show answer & explanation
Correct answer: D - $480,000 at completion, requiring $30,000 above the approved budget.
Question 10
After several missed activation dates, a regional lead tells the project manager, 'We understand the protocol, but our site leads will not contradict the senior director in an open call.' The dates had been accepted without discussion of local staffing. What adjustment would make the next multinational planning cycle more reliable?
Show answer & explanation
Correct answer: C - Obtain site capacity estimates privately in advance, then confirm achievable dates and owners together.
That's 10 of 1,030
The full bank has 1,020 more ACRP-PM questions with explanations.